Project Details

Project summary

Replace existing systems in W.I.F & W.I.C

Location

NHS Hospital, Essex

Equipment

2 x Danfoss Optyma Plus condensers
2 x Searle TEC evaporators

About the project

The existing systems in both the walk in freezer and walk in chiller were dated, inefficient and not operating as well as they should be so we were asked to remove these and install new equipment. These were also accompanied by new pipework, medium duty cable tray and new electrical supplies. The condensers were installed on the flat roof above the kitchen. Due to the existing rooms being just as old as the existing systems, they had a new floor installed in both rooms with 5 bar checkaplate for anti-slip protection as well as a new door heater for the walk in freezer.